Front | Back |
Use the project scope statement to gain approval of the a final" scope from stakeholders before further planning is done.During Which Process Group ? Is This Done
|
Planning Process
|
Determine high-leave requirements, constraints, assumptions, and risks.and risks.During Which Process Group ? Is This Done
|
Initiating Process
|
Measure against the performance measurement baselineDuring Which Process Group ? Is This Done
|
Monitormgand controlling
|
Implement approved changes, including corrective actions,preventive actions, and defect repair.During Which Process Group ? Is This Done
|
Executing
|
Reanalyze existing risks.During Which Process Group ? Is This Done
|
Monitormgand controlling
|
Use the high-level planning and estimating data to determine whether the product can be achieved within the given constraints.During Which Process Group ? Is This Done
|
Initiating
|
Verify and document that the project, or project phase, meets completion or exit criteria set in place during the planning process groupDuring Which Process Group ? Is This Done
|
Closing
|
Hold team-building activity During Which Process Group ? Is This Done
|
Executing
|
Evaluate the effectiveness of risk responses in a risk auditDuring Which Process Group ? Is This Done
|
Monitormgand controlling
|
Determine how you will plan scope, time, cost, quality, human resources, communications, risk, procurement, and process improvement and put that information into the beginnings ofmanagement plans.During Which Process Group ? Is This Done
|
Planning
|
Obtain formal (legal) sign-off and final acceptance of the product of the project from the customerDuring Which Process Group ? Is This Done
|
Closing
|
Increase the etfectivenes of processesDuring Which Process Group ? Is This Done
|
Executing
|
Recirculate how much the project will cost and how long it will take, and create forecastsDuring Which Process Group ? Is This Done
|
Monitormgand controlling
|
Plan what will be communicated on the project, to whom, bywhom, when, and how.During Which Process Group ? Is This Done
|
Planning
|
Spend time trying to improve qualityDuring Which Process Group ? Is This Done
|
Monitoringand controlling
|