Which of the following describes the technique of poka-yoke (mistake proofing)?
An airline pilot reviews a pre-flight checklist to make sure everything is ready for takeoff.
Justin Thyme used to run one batch each of 500 As, 300Bs and 100Cs every month but now he runs a batch of 5As, 3Bs, and 1C every half day:
now that he embraces mixed-model assembly
In lean systems, if a defective product is found, which of the following is generallyNOT done?
The defective unit is passed on to the next workstation. 82.609%
In lean systems, if a defective product is found, which of the following is generally done?
The production line is stopped. 13.043% The defective unit is passed on to the next workstation. 82.609% The defective unit is returned to the worker responsible for creating the defect. 1.449% The production line is made aware of the problem without stopping the line.
If the inventory advantages of a lean system are to be realized, small lot sizes must be used; in order to use small lot sizes, manufacturers must significantly reduce setup times because:
Reduced setup time makes small lot sizes economical.
Demand scheduling is a type of scheduling that:
assigns customers to a specific time for order fulfillment
A _____________________ specifies the sequence in which jobs or activities should be processed.
dispatch list
The time from when a job enters a workstation to when it is finished is called
flowtime
A job with a critical ratio of 1.2 is
ahead of schedule
Characteristics of lean systems
Pull method of work flow, quality at the source, small lot sizes, uniform workstation loads, standardized components& work methods, close supplier ties, fleixble workforce, preventive maintenance, line flows, automation five S.
A companywide process that cuts across traditional functional areas, business units, geographic regions, and product lines is a(n):
enterprise process.
Which one of the following statements concerning MRP is true?
MRP is appropriate for use in environments with many BOM levels and an assemble-to-order strategy
The time-phased plan specifying when and how many end items are to be built is known as the:
master production schedule
Any item manufactured from one or more components is a(n):
Parent
Which best defines the gross requirements for a component item?
the total demand for the component derived from all immediate parents