What type of contract works with a very well defined scope?
|
Fixed price
|
A hybrid type of contract that could contain aspects of both cost-reimbursable and fixed price type arrangements.
|
T & M
|
Collect Requirements -> ? -> Create WBS -> Verify Scope -> Control Scope.
|
Define Scope
|
? -> Define Scope -> Create WBS -> Verify Scope -> Control Scope.
|
Collect Requirements
|
Collect Requirements -> Define Scope -> Create WBS -> ? -> Control Scope.
|
Verify Scope
|
Risk categories can be ...(4 of them)
|
Technical, external, organizational, and project management risks.
|
Requirements traceability matrix is an output of what?
|
Collect Requirements
|
The Requirements traceability matrix is used to trace requirements to ___, objectives, and _____
|
project scope, to objectives, and to test strategy.
|
7 Basic Tool of Quality are.....
|
1) cause & effect diagram, 2) control charts 3) flowcharting 4) histograms 5) pareto chart 6) run charts 7) scatter diagrams.
|
In a cause and effect diagram, the potential cause of a specific effect fall into these 8 categories:
|
Time, machine, method, material, energy, measurement, personnel, and environment.
|
General mgt techniques to generate different approaches to doing work
|
1) Lateral thinking
2) Six Thinking Hats 3) Brainstorming |
Lateral Thinking
|
Lateral Thinking is part of Alternative Identication which is tools and technique of Scope Definition.
It is thinking out of the box! |
The date through which the project had provided actual status and accomplishments is called the...
|
Data date..aka as-of Date or Status Date.
|
Tools and techniques recommended for developing a project team
|
Training, team building, and ground rules.
|
A tool/technique that is common to all Project Integration Management processes.
|
Expert Judgement
|