Define the process of developing the project Charter.
|
It is the process of developing a document that formally authorizes a project or a phase and documenting initial requirements that satisfy the stakeholder's needs and expectations. In multiphase projects, this process is used to validate or refine the decisions made during the previous iteration of develop project charter.
|
What are the Inputs for Developing a Project Charter?
|
1. Project Statement of work 2. Business case 3. Contract 4. Enterprise environmental factors 5. Organizational process assets
|
What is(are) the output(s) from the Develop Project Charter process?
|
1. The Project Charter
|
What are the Inputs for the process of identifying stakeholders?
|
1. Project charter 2. Procurement documents 3. Enterprise environmental factors 4. Organizational Process assets
|
What is(are) the output(s) from the Identify Stakeholders process?
|
1. Stakeholder register
2. Stakeholder management strategy |
Define the Planning Process Group
|
The Planning Process Group consists of those processes performed to establish the total scope of the effort, define and refine the objectives, and develop the course of action required to attain those objectives.
|
What are the Inputs for developing a Project Management Plan?
|
1. Project charter 2. Outputs from planning process 3. Enterprise environmental factors 4. Organizational process assets
|
What are the outputs of Developing a Project Management Plan?
|
A project management plan
|
Define the Collect Requirements Processes
|
The Collect Requirements process is the process of defining and documenting stakeholders needs to meet the project objectives.
|
What are the inputs to the Collect Requirements Process?
|
1. The Project Charter 2. The Stakeholder register
|
What are the outputs to the Collect Requirements Process?
|
1. Requirements documentation 2. Requirements management plan 3. Requirements traceability matrix
|
Define the Defining Scope process.
|
Defining Scope is the process of developing a detailed description of the project and product.
|
What are the inputs to the Defining Scope Process?
|
1. Project charter 2. requirements documentation 3. organizational process assets
|
What are the outputs of the Defining Scope Process?
|
1. Project scope statement 2. Project document updates
|
Define the Create Work Breakdown Structure process.
|
It is the process of subdividing project deliverables and project work into smaller, more manageable components.
|